Notice ID: | 49634 |
Notice Type: | Planned Service Outage |
Critical: | Y |
Notice Status Description: | Initiate |
Reqrd Rsp Desc: | No Response Required |
Posting Date/Time: | Nov 20 2024 12:57PM |
Subject: | December 2024 --- FGT SUPPLY AREA MAINTENANCE IN Zone 3 |
Notice Effective Date/Time: | Dec 1 2024 9:00AM |
Notice End Date/Time: | Dec 31 2024 9:00AM |
Notice Text: |
FGT will be performing pipeline maintenance near FGT Compressor Station 10. This maintenance will begin December 1, 2024, and is to be completed by the end of gas day on December 14, 2024. During this maintenance, FGT may schedule up to 1,200,000 MMBtu/day through Station 10. During normal operations, FGT schedules up to 1,300,000 MMBtu/day through Station 10. FGT will be performing maintenance at FGT Compressor Station 11. This maintenance will begin December 2, 2024, and is to be completed by the end of gas day on December 6, 2024. During this maintenance, FGT may schedule up to 2,500,000 MMBtu/day. During normal operations, FGT schedules up to 3,250,000 MMBtu/day through Station 11. FGT continues to perform pipeline maintenance near FGT Compressor Station 12. This maintenance will continue through December 31, 2024. During this maintenance, FGT may only be able to schedule up to 2,800,000 MMBtu/day range through FGT Compressor Station 12. During normal operations, FGT schedules up to 3,175,000 MMBtu/day through FGT Compressor Station 12. |